Our solutions on construction site : Water
Our products on construction site : Macro-trenchers
The needs on this site : Rental
Location : 29410 pleyber-christ
Initial issues
As part of a GRDF-led gas pipeline project in Pleyber-Christ (Finistère, France), the EIFFAGE Réseaux – LAGADEC Réseaux consortium was tasked with installing a DN160 HDPE gas pipe.
LAGADEC Yvon TP, responsible for one section of the project, was looking for a mechanised trenching method that could address several key priorities:
Groupe Marais was selected to meet these requirements through its France Rental Division – Sector 1 Operations. A Marais GD2 offset wheel trencher was deployed, ideally suited for working along roadways closed to traffic.
The project was carried out with a carefully planned and streamlined process:
The project was delivered on time with 4,000 linear meters of trenching completed within the planned schedule.
Key benefits included:
Noël PERRIN – Operations Manager, LAGADEC Réseaux (29)
"The GRDF tender for this project was of particular interest to us due to its geographic proximity to our company and the opportunity it offered to test and refine our site procedures, especially regarding the new HDPE gas pipe wrapping techniques using geotextile.
Our knowledge of the area and its stakeholders enabled us to prepare a technical submission that was well adapted to the project requirements.
We can confidently say that this project is fully aligned with our company’s CSR commitments — we are currently undergoing certification.
The rural location was well suited to wrapped installation. We were able to unroll the HDPE pipe and install the recycled geotextile the week before trenching, preparing only a few conventional trenches for driveway crossings and an intersection.
After wrapping, we completed the connection sleeves between each reel before the MARAIS trencher passed through, equipped with a dedicated laying box.
Preparing the sleeves in advance was a real time-saver, as it significantly reduced the need for handling operations at each reel change — which can sometimes be delicate and involve working at height above the trencher. This helped us lower the accident risk on site.
We were also able to reuse materials extracted from the site, particularly by screening rocky areas and processing them at our own valorisation platform in Pleyber-Christ.
As a result, our carbon footprint was reduced. This method fits perfectly within our CSR policy, especially considering our involvement in green gas development."
Marais SA
Zone d'activité "Les portes de l'Anjou"
1, rue Pierre et Marie Curie
49430
Durtal - France
Phone +33 2 41 96 16 90