Our solutions on construction site : Electricity
Our products on construction site : Macro-trenchers
The needs on this site : Rental
Location : 75000 Paris
Client : Razel-Bec
Projet : Installation of networks in the Grand Paris Tunnel - Line 16
Service : Location
Activité : Electricity
Date : March 2024
Problématique du client
Laying all primary and secondary ducts over 15 km inside the tunnel of Line 16 of the Grand Paris respecting all the requirements of the Société du Grand Paris.
Solutions
In front of this technical challenge and in collaboration with our customer (Razel-Bec), we’ve realized this difficult jobsite.
Thank to Marais specific and customized laying box system, we’ve been able to simultaneously lay 15 x HDPE ducts of 40 mm and 18 x 32 mm for the secondary network with progressive concrete pouring. For the primary network instead, we’ve laid 30 x HDPE ducts of 32 mm.
Resultats
This strategic choice, aimed at optimizing the concrete pouring and preventing any blockage during the laying, enabled us to achieve a performance up to 600 linear meters of full ducts installation per day.
Machine
Tesmec trencher 985 Chainsaw
Marais SA
Zone d'activité "Les portes de l'Anjou"
1, rue Pierre et Marie Curie
49430
Durtal - France